ALPES Aluminum Windows and Doors GCC Certification: The Gulf Mark Does Not Cover Windows, and the Factory Cannot Hold Your Certificate

Date: Oct 12 2026 标签arcclick报错:缺少属性 aid 值。
Read this before you copy anything out of it. This article describes how Gulf conformity works and how to check a claim. It is not a list of numbers to paste into a submittal, a specification or a purchase order. Certificate scopes, standard editions and national schemes move, and several of them moved recently. Everything here that came from outside this company is labelled as such. Take the method, not the values, and ask us for the actual document before you rely on it.

Buyers ask us for "GCC certification" for aluminium windows and doors, and the honest answer is that the question has three different answers depending on which layer you are standing in. There is a Gulf standard, which is a document. There is a Gulf conformity mark, which is a scheme that, on the published list of regulations that carry it, does not currently cover construction products. And there are six national systems, one per member state, none of which accepts another's certificate as a substitute.

Two sentences carry the whole article. First: a Gulf standard number on a datasheet is a technical claim about a product, not a document that gets a container through customs. Second: the certificate that actually clears your shipment is held by the importer, not by the factory — so the one question we cannot answer yes to is the one buyers most want us to.

Four things the phrase "GCC certification" gets used to mean

Almost every disagreement we have had on this topic came from two people using the same three words for different objects. Here they are separated.

What the buyer is usually picturing What it actually is Does it clear a window through customs What to ask for instead
"It meets GSO [number]" A standard published by the Gulf standards body. A document, not a certificate. No. Gulf standards are not directly binding. They become enforceable only when a member state adopts them into national law. The number, the edition year, and the test report from an accredited laboratory showing that specimen met it.
"It has the G mark / GCC mark" The Gulf Conformity Mark, a regional scheme run under a short list of approved Gulf technical regulations. Not for our product. Construction products appear on the published list of planned regulations, alongside machinery, lifts and gas appliances, with no timetable given. The regulation number, the notified body identifier, and the QR code. See the ten-second test below.
"It is SABER registered" (Saudi Arabia) A national two-stage system: a Product Certificate of Conformity and a Shipment Certificate of Conformity. Yes, in Saudi Arabia only, and both documents are needed. Which of the two the supplier is talking about. They are not interchangeable.
"It is ECAS / EQM certified" (UAE) National schemes run by the federal industry ministry through appointed notified bodies. Depends on the product category, and public sources disagree about whether aluminium window systems are inside the mandatory list. Whether your category is on the current regulated list, and who your consultant will accept instead.
"The factory is GCC certified" Usually a sentence on a website rather than an instrument anyone can look up. No. Certificate number, issuing body, applicant name, scope text, and expiry. If any of the five is missing, you do not have a certificate.

The Gulf standard for a window is the European standard, and that is worth knowing

A public standards database records GSO EN 14351-1:2011 — "Windows and doors, Product standard, performance characteristics, Part 1: Windows and external pedestrian doorsets without resistance to fire and/or smoke leakage characteristics" — published by the Gulf standards body in 2011 under classification 91.060.50 for doors and windows. The same record lists the adopted standard as EN 14351-1:2006.

Read that again, because it changes what a compliance claim means. The Gulf standard for our product is an adoption of the European one. A supplier saying "we meet the Gulf standard" and a supplier saying "we meet EN 14351-1" may be making the same claim wearing two different covers. That is not a trick and it is not a reason to distrust either statement — it is the structure of the system.

Two documents can share a number without being the same document

Here is the part that catches people. The European route is commonly cited as EN 14351-1:2006 plus amendment A1:2010. The Gulf adoption recorded in the database we checked references the 2006 base text. We are reporting what the databases say rather than adjudicating them, and you should verify the current edition with the standards body before citing either — but the practical consequence is simple:

"Meets EN 14351-1" is not a complete answer. Ask which edition, and ask whether the amendment is inside the claim. A test report issued against one edition is a report about that edition.

There is a second version of the same trap. The same standard number also appears as OS GSO EN 14351-1:2011, published by a national specifications and metrology directorate rather than by the regional body. So the identical string can exist twice: once as a Gulf standard and once as a national standard of one member state. Both can be true at once, and neither replaces the other.

This is the reason we do not put a standard number in a quotation without its year attached. The number is the easy half. The year is the half that decides what was actually tested.

The ten-second test: look for the QR code

You do not need to know anything about windows to run this check, which is why we lead with it.

Where the Gulf Conformity Mark genuinely applies, it is affixed by the manufacturer or its authorised representative on the strength of an assessment by a notified body, and since April 2017 the mark has had to carry the notified body identifier and a QR code linking to the tracking system. A procurement advisory source puts the consequence in one line: a mark image with no QR code is not a current mark.

So when a supplier sends you a picture of a logo, look for three things in ten seconds:

  • A QR code. No code, no current mark.
  • A notified body identifier. Someone has to be named. A mark with no issuer is a graphic.
  • A regulation number. Not a product name, not a series name. The instrument the assessment was carried out against.

We would rather hand you that test than hand you a certificate number. A test you can run yourself is worth more than a number you have to take on trust.

The count test: the bloc has six members

The Gulf Cooperation Council has six member states: Bahrain, Kuwait, Oman, Qatar, Saudi Arabia and the United Arab Emirates.

We have read certification consultancy pages describing the mark as legally mandatory in "all seven GCC member states", with the seventh named as Yemen. We are not going to adjudicate Yemen's standing in a standards body from a factory in Foshan, and we are not going to name the consultancies. But when a seller's own headcount of the bloc is off by one on their own product page, that is useful information about how carefully the rest of the page was written.

Counting is free. Do it before you read anything else on the page.

The contradiction we are not going to resolve for you

This is the part of the topic where we think buyers get worst served, so we are going to describe it rather than smooth it over.

On one side: public pages from certification consultancies describe the Gulf mark as covering building materials. The scope lists they publish differ from each other — one names tiles, steel, pipes and paints; another names steel, cables and bathroom equipment; and at least one article written specifically for doors-and-windows exporters names doors and windows as one of six core categories under a described building materials scheme, complete with named Gulf technical regulation numbers, numerical thresholds, a stated certification timetable and a certificate verification portal address.

On the other side: the published list of Gulf technical regulations that actually carry the mark has five entries — general product safety, the marking regulation itself, toys, low voltage electrical equipment and appliances, and water consumption conservation products. Construction products are on the separate list of planned regulations, alongside machinery, lifts and gas appliances, with no published timetable.

We are not going to tell you which side is right, and we are not going to repeat the numbers from either side, because repeating them is how a number from a marketing page ends up in a submittal. What we will tell you is what the disagreement means: the people who sell the certificate and the scheme that issues it do not agree on whether it exists for our product. Any figure you take from either camp is a figure you now own.

And here is the uncomfortable part. We are the party with the strongest motive to say yes. A factory that answers "yes, we have GCC certification" in one line is answering the question you asked rather than the question you needed answered. That is exactly why you should not take a yes from us, or from anyone else, without the QR code.

Saudi Arabia: the one market where our product has a named regulation

Saudi Arabia is where the discussion stops being abstract. There is a Technical Regulation for Doors, Windows and their Accessories, its published scope covers doors, windows and building hardware, and it is administered through the SABER platform.

Two documents, and they do not do the same job

Under SABER, conformity is split into two certificates:

  • Product Certificate of Conformity (PCoC) — issued once per product model. It lives with the model.
  • Shipment Certificate of Conformity (SCoC) — issued for each shipment. It dies with that shipment.

Both are mandatory. One is not a substitute for the other, and this is where a lot of project schedules quietly break: a supplier can genuinely hold a valid product certificate and still have nothing that clears next month's container.

There is one more detail that matters more than both of those, and it is the answer to the question we get asked most often. The importer is required to obtain the SABER product certification. It is issued by a notified certification body, but the applicant is the importer. We can be the subject of that certificate. We cannot be its holder. If a factory tells you it holds your Saudi product certificate, ask to see the applicant name on it.

Count the standards list: it is mostly about hardware

A publicly published conformity guide lists the standards referenced by the Saudi doors-and-windows regulation. Read the shape of the list rather than the individual entries:

  • Six entries name a material. Two of them are ours: SASO-1033 aluminium windows and SASO-1034 aluminium doors. The others cover wooden windows, wooden doors, fire doors, and rigid PVC extruded hollow profiles.
  • Thirteen more entries name a piece of hardware, and every one of them is a European EN standard with a national prefix on the front: single-axis hinges, corrosion resistance of hardware, controlled door closing devices, electrically powered hold-open devices, door closers, mechanical durability and strength, hardware for windows and door-side windows, cylinders and accessories, operating forces and kinematics, lever handles and knobs, panic exit devices, emergency exit devices, and more.
  • One of those hardware entries is published in sixteen separate parts.
The regulation spends more of itself on the hardware than on the material. If a supplier can only talk to you about profile thickness and alloy temper, they have read the smaller half of the document. Our hardware comes from named German and European houses, which is relevant here precisely because the list is written in that language — but the relevance only becomes evidence when there is a test report behind it, from an accredited laboratory, for the configuration you are actually buying.

Two further practical points from the same public sources. First, the product types that additionally require a factory audit are identified as fire-resistant doors, windows and hardware. That single line decides whether someone has to physically visit the plant, so settle it early rather than in week six. Second, labelling is part of conformity, not packaging: Arabic, or Arabic and English; firmly attached and not easily removable; carrying the product description, model name or number, the trademark or manufacturer name, and the country of origin in a "Made in" format. Label artwork has to be designed before production, not at the container.

One honest note about catalogue scope. The same regulation's list includes rigid PVC profiles and wooden doors and windows. A pvc folding door and a solid wood entry door are both inside that regulation's scope and outside what we make. If your schedule contains either, that line of the schedule belongs to a different supplier and a different certificate — and it should be identified as such before the submittal goes in, not after.

Kuwait: the same two-tier idea, built independently

Kuwait runs a conformity assurance scheme with a dedicated building and construction group, administered by the public industry authority. Its published category lists name ceramic tiles, cement, gypsum, conduits, sanitaryware, pipes, reinforcement bars and masonry units.

What makes Kuwait worth its own section is that it separates the two documents even more explicitly than Saudi Arabia does:

Document What level it works at How long it lasts What people get wrong
Technical Evaluation Report Product level. Confirms the product meets the applicable national, Gulf or international standard. Tracks the validity of the underlying test report. Reusable across shipments. Assuming it clears a consignment on its own. It does not.
Technical Inspection Report Consignment level. Confirms this shipment meets the import requirements. One shipment only. Treating last time's report as if it still applies. It expired with the previous vessel.

Both have to accompany a consignment containing regulated products. Now put that next to the Saudi pair and the pattern is unmistakable: two countries, two naming systems, one identical structure — a document about the product that outlives shipments, and a document about this shipment that does not. Nobody coordinated this. It is simply what a border needs: something that says what the thing is, and something that says what is in this box.

The scheduling consequence is the expensive one. Kuwait does not permit the assessment to be done on arrival. It happens in the country of export, before the goods sail, by an authority-authorised body. A buyer who treats it as a destination formality has already lost the sailing.

Kuwait also carries national deviations that catch a specification copied from elsewhere. Country of origin has to be marked on each product rather than only on the packaging. Instruction material for anything a consumer will operate has to be in Arabic and English. These are small requirements with a long tail if they are discovered at the port.

The UAE: the grey area, described by someone who sells into it

The UAE is the market where we have completed villa projects in Saudi Arabia and Dubai, and it is also the market where the honest answer is most uncomfortable, because the answer is "it depends who is asking".

Start with the thing everyone assumes. A European aluminium fabricator's own public guidance says it plainly: a CE mark travels with the product, not with the building, and what it certifies is a factory production control regime rather than project compliance. The same page states that CE marking is a European regulatory framework and has no legal standing in the UAE. We use German hardware and European-derived test methods, so this sentence costs us something to repeat. We are repeating it anyway.

The federal framework runs through two routes. Per a compliance consultancy's public description: ECAS is the mandatory conformity route for regulated products, valid for one year and renewed annually, and is document-driven with no factory audit. EQM is a voluntary quality mark, valid for three years, adding a factory quality-management audit and testing, and it can substitute for ECAS at customs. Notified bodies named in that description include the large international inspection groups, and testing is carried out by nationally accredited ISO/IEC 17025 laboratories.

Then comes the part that matters for us. The same European fabricator's guidance states that aluminium window and door systems do not currently fall under the same mandatory product certification as, for example, electrical equipment, and that this creates a grey area which many people misinterpret as meaning there are no conformity requirements at all. There are. They operate through different channels:

Route Who decides What they want What people get wrong
Municipal laboratory testing and verification The municipal testing and certification department, particularly on government projects and in certain zones. Testing or verification of existing certifications through the municipal laboratory. Assuming it applies to every plot. It applies where the authority having jurisdiction says it does.
Consultant-driven specification The architect or facade consultant. This is the most common route on private work. Performance test reports from an accredited laboratory, commonly covering air permeability, watertightness, wind resistance and thermal transmittance. Treating acceptance as a regulation. The operative word is accepted, not required.
Developer approved lists Major developers with their own material lists, which can exceed code minimums. Their own combination of European and local requirements. Assuming the code minimum is the bar. On some projects it is the floor.
Free zone authorities The free zone itself, with its own approval process. Whatever that zone's process says. Assuming the mainland municipality process transfers into the zone.
In the Gulf's busiest market, the gate is usually a person rather than a portal. Find out whose. Ask your consultant, in writing, which route applies to your plot and which accreditation marks they will accept on the test reports. That single question does more for your schedule than any certificate we could send you.

European test evidence still does most of the work in a UAE submission. It simply has to be presented against the right route. The commonly named test standards for glazing submissions are air permeability, watertightness, wind resistance and thermal transmittance under their European numbers, with reports from laboratories holding recognised national accreditations.

And one more contradiction, offered without adjudication: we have also read public guidance stating that doors and windows are a regulated category under the federal ministry, and that applicants for the certificate can be exporters, distributors, traders or manufacturers. Note that this is the opposite of the Saudi position, where the importer applies. Two public sources, two different answers on both scope and applicant. Do not resolve that from a blog — resolve it from your consultant and your notified body.

Oman, Bahrain and Qatar: the one that changed, the one that waits, the one that reads

Oman: a new mark, and three licences rather than one

Oman introduced a national quality mark by ministerial decision, with building materials in scope — published ministerial statements name cement, ceramics and porcelain, with other reporting mentioning plastic pipes, steel and electrical components. The requirements described include laboratory testing and a factory audit, the audit being a visit to the plant, and licences for the manufacturer, the importer and the distributor.

Three licences, not one. If nobody on your project has asked who holds the importer's licence and who holds the distributor's, nobody has read the decision. This is also the market where published sourcing advice is most likely to be out of date, because the scheme is recent and changed at a stated date.

Bahrain: the answer really is "on arrival"

Bahrain has no pre-shipment conformity scheme for these products. Control happens on arrival, run by the standards and metrology directorate, which has an office inside the main port. The regulated list relevant to construction is short — cement and asbestos are named — and controlled products enter on conformity assessment certificates from internationally recognised bodies.

The consequence is oddly counter-intuitive: Bahrain is the market where "we already have the certificate" is worth least, because there is no certificate to have. It is also the market where commercial websites are most likely to be wrong — some describe a pre-shipment inspection requirement or borrow the neighbouring scheme entirely. Check the current position with your importer rather than with a search result.

Qatar: the port is quiet, the submittal is not

Qatar's pre-shipment certificate requirement exists, but its regulated product list is narrow and leans towards vehicles and appliances — tyres, seat belts, rims, brake pads, exhaust fans, irons and hair dryers are the kind of entries named. Building materials and building products do not appear on it.

That does not make Qatar easy. The real gate is the national construction specification, issued by ministerial decision and published in the official gazette, replacing the previous edition. It is imposed through the contract rather than inspected at the port, and the consultant reviews test reports at material submittal.

Routine documentary requirements still apply to consignments regardless: a certificate of origin showing the classification code and country of origin, commercial documents attested by the chamber of commerce in the country of export, and under letters of credit, notarisation through the relevant Arab embassy, consulate or chamber.

In Qatar the container is not the gate. The material submittal is the gate. Budget your lead time for the consultant's review, not for the port.

Six states, six answers: the comparison table

Market Is our product inside the named scheme Where the check happens Who has to hold the document What nobody tells you
Saudi Arabia Yes. Doors, windows and accessories are a named regulated category with their own technical regulation. On the platform, before the shipment arrives. The importer. You need two certificates, and only one of them is about the product.
Kuwait A building and construction group exists; published categories are heavy materials rather than finished window systems. In the country of export, before sailing. Arranged through an authority-authorised body, carried with the consignment. Assessment on arrival is not permitted. Miss the pre-shipment window and you miss the vessel.
United Arab Emirates Disputed in public sources. A grey area, not an exemption. Through the municipality, the consultant, the developer or the free zone, depending on the plot. Varies by route; several public sources name different applicants. CE marking has no legal standing here. European evidence is accepted as evidence, not as approval.
Oman Building materials are in scope under the national quality mark. Testing plus a physical factory audit, then licensing. Manufacturer, importer and distributor each need a licence. Three licences. Most schedules only budget for one.
Qatar Not on the pre-shipment regulated list. At material submittal, not at the port. The consultant imposes the construction specification through the contract. A quiet border does not mean a quiet specification.
Bahrain A short controlled list, mostly cement and asbestos for construction. On arrival, at the port. Controlled products enter on certificates from recognised bodies. Commercial sites invent pre-shipment requirements here. They are describing another country.

What we publish, what you have to go and get

This is the table we would most like a buyer to read, because most of the friction on Gulf projects comes from expecting a factory to hold a document that no factory can hold.

Item Do we have it Why the gap exists, or why the number will not travel
Alloy grade and profile thickness range Published for named series. A material declaration, not a performance result.
Thermal break material Published. Names the material. It does not give you a thermal figure for your opening.
K values for named series Published for specific series. These are system values, not whole-window values, and they are not the rating your authority will ask for. A thermal number is the product of a size, a configuration, a glass build and the standard it was calculated under. Change any one and it is a new number.
Salt spray hours and shear value Published for one named series. They measure coating and substrate, and the composite bond between the strip and the aluminium. Neither is an air, water or wind rating, and neither transfers to another series.
Hardware brands and cycle figures Published for specific hardware. A cycle figure is a rig test on a component. It is not a service life for a window, and a handle cycle is not the same test as a loaded sash cycle.
Test reports to the standards your consultant names To be requested for your configuration. A report names a specimen, a size and a glass build. Yours is not that specimen until someone tests yours.
Laboratory accreditation You specify it, we comply. Several Gulf routes require accredited laboratory reports. Name the accreditation in the enquiry, not after the test.
Quality management certificate Available on request. Several schemes ask for it as an input document. It is not a product certificate.
Factory audit We can host one. Required only for certain scopes under the Saudi regulation. Confirm early, because it is the item with the longest lead time.
Arabic labelling artwork Produced to your required content. Labelling is part of conformity. It has to be designed before production.
Certificate of origin, supplier declaration, risk assessment Produced per shipment. Shipment documents. They cannot exist before there is a shipment.
Your national product certificate We cannot hold this. In Saudi Arabia the importer is the applicant. In other markets it may be a different party again. We can be the subject of the certificate and the source of its evidence, never its holder.
Your project approval We cannot hold this. An approval attaches to a building and an authority. It is not a property of a product.

The part we would rather say ourselves

We make aluminium windows and sliding doors in Foshan and Zhaoqing. Three of the things buyers most often ask us for are things we do not have, and saying so now is cheaper than saying it in week eight.

  1. A Gulf Conformity Mark for a window. On the published list of regulations that carry that mark, construction products are in the planned column with no timetable. We are not going to sell you one, and we are not going to describe something else in words that sound like one.
  2. Your national product certificate. Someone in your country has to apply for it. We can be named in it and we can produce the evidence that goes into it, but the applicant is not us.
  3. A CE mark with Gulf legal effect. It does not work that way. A European mark certifies a production control regime under a European framework; it has no legal standing in the UAE, and it is accepted elsewhere as evidence of performance rather than as approval.

What we can be is a factory that produces checkable evidence: material declarations, section drawings, profiles, test specimens, accredited reports, and a plant that can be audited. That is a smaller claim than "certified" and a more useful one.

One more thing we would rather say than have you discover. Our folding door, swing door and entry door category pages are empty. If your schedule includes wood bi fold doors, we are not the supplier for that line, and pretending otherwise to keep an enquiry alive is how a submittal gets built on a product that does not exist.

Twelve lines you can paste into an enquiry

Fill these in and send them to any supplier, including us. The third column is what happens when the line is left blank.

Line What a good answer looks like If you leave it blank
Destination country and port Named country and named port. Nobody can tell you which scheme applies, because six of them exist.
Name of the national instrument The actual regulation or scheme name, not "GCC". You get a regional answer to a national question.
Who is the applicant A named company in the destination country. Everyone assumes someone else is doing it.
Product-level document required Named document, with its own validity rule. You budget for one certificate when the scheme needs two.
Shipment-level document required Named document, plus who applies and how far before sailing. A valid product certificate and a container that still cannot clear.
Test standards and editions Number plus year, and whether amendments are included. You accept a report against an edition your consultant will not take.
Laboratory accreditation required The accreditation mark your authority accepts, named. The test gets done twice, and the second time is on your schedule.
Specimen size and glass build The actual dimensions and glass make-up of the tested unit. A rating for a specimen that is not the one on your elevation.
Is a factory audit required Yes or no, with the scope that triggers it. The longest lead-time item in the whole file gets found last.
Labelling language and content Language, and each required field. Compliant windows with non-compliant labels.
Marking of origin Whether on each product or only on packaging. A deviation that is cheap in production and expensive at the port.
Who signs the submittal A named consultant or engineer, and their acceptance route. You optimise for a portal in a market where the gate is a person.

Ten answers that sound reasonable and carry no information

The answer you get Why it is empty Ask instead
"Yes, we have GCC certification." No instrument called that covers a window on the published list. Which regulation number, which notified body, and where is the QR code.
"It is CE marked, so it is fine for the Gulf." A European mark has no legal standing in the UAE. Which route on my plot accepts it, and who says so in writing.
"Our factory is ISO 9001." An input document for several schemes. Not a product certificate. The product certificate that the scheme actually requires.
"The hardware is German." Relevant to the hardware half of the standard list, and still not a result. The hardware test reports, and the standard numbers they were run against.
"We have test reports." A report names a specimen, and yours is not it by default. The specimen size, the glass build, the edition, and the lab accreditation.
"It is on the GSO list." Being on a planned list is not being in a scheme. Which list, which column, and what the entry says.
"The certificate covers the series." Approval attaches to a configuration, not to a marketing name. Does the scope text name my size, glass build and opening type.
"The agent will handle it." Handling is not holding. Someone still has to be the applicant. Whose name appears as applicant on the certificate.
"It passed in another Gulf country." There is no regional equivalence for national certificates. What is required in my country, from my authority, in writing.
"Send us the certificate later." Later is after the container has sailed. Send it now, or put the requirement in the contract with a date.

Questions we get asked

Can you send us your GCC certificate?

Not in the form the question usually means. We can send the things a certificate is built from: material declarations, drawings, accredited test reports for a stated configuration, our quality management certificate, and an invitation to audit the plant. The certificate itself names an applicant in your country, and that is the one document we are structurally unable to hold.

Is a Gulf standard number the same as a certificate?

No. Gulf standards are not directly binding; they become enforceable when a member state adopts them into national law. A standard number on a datasheet is a technical claim about a product. The document that moves a consignment is always the national one.

Does CE marking help at all?

Yes, as evidence, and no, as approval. European test evidence does most of the practical work in a Gulf submission, but it has to be presented against the route your authority accepts. It has no legal standing in the UAE, and it is not a substitute for a national certificate anywhere.

Why do you insist on the QR code?

Because it is the one check that needs no expertise. Where the regional mark genuinely applies, it has carried a notified body identifier and a tracking QR code since 2017. A logo without them is a picture. We would rather give you a test you can run than a number you have to believe.

Which of your published numbers actually matter for compliance?

Fewer than buyers hope. Alloy grade, profile thickness and thermal break material are declarations. Thermal values are system values, not whole-window ratings under the scheme your authority uses, and they change with size, configuration and glass build. Salt spray hours and shear values belong to one named series and measure coating and composite bond, not air, water or wind. None of them is the rating a Gulf submittal asks for.

How early should we start?

Earlier than the drawing schedule suggests. The items with the longest lead times are the factory audit where a scope triggers one, the accredited test on your actual configuration if one is needed, and the pre-shipment assessment in the country of export where the scheme requires it. None of those can be compressed once the vessel is booked.

The short version

  • There is no single Gulf certificate for an aluminium window. There is a standard, a mark that does not currently cover construction products, and six national systems.
  • A Gulf standard number is a technical claim, not a customs document. The enforceable instrument is always the national one.
  • The Gulf standard for windows is an adoption of the European one. Ask for the edition year, because a number without a year is not a document.
  • The bloc has six members. If a page says seven, read the rest of it more carefully.
  • Where the regional mark applies, it carries a notified body identifier and a QR code. No code, no current mark.
  • Certificates do not travel between member states. Four parallel national programmes have to be satisfied on their own terms.
  • Saudi Arabia splits conformity into a product certificate and a shipment certificate. You need both, and only one is about the product.
  • Kuwait built the same split under different names, and does not permit the assessment on arrival.
  • In the UAE the gate is usually a person. Find out whose, in writing, before you optimise for a portal.
  • The importer holds the certificate. We can be the subject of it and the source of its evidence, never its holder — and we would rather say that now than in week eight.
Do not copy a number out of this article. Certificate scopes, standard editions and national schemes move, and several of them have moved recently. Use this to work out which questions to ask and who has to answer them. Then get the answer from your authority, your consultant or your notified body, in writing, with a date on it. A page like this one is for understanding the shape of the problem. It is not a source of values.